Resource Management
William is a project manager and he has to publish a project schedule. His next step after activities, start and end times and resources are identified would be:
Distributing the project schedule according to the communications management plan.
Refining the project management plan to reflect more accurate costing information.
Confirming the availability of the resources.
Publishing a bar chart illustrating the timeline.