PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconResource Management

Sofia is a project manager leading a cross-functional project team in a weak matrix environment. Team members don't report to her functionally and Sofia has limited ability to directly reward them. The project itself is very challenging. Which type of project management power would be the most effective for Sofia to use?