PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconResource Management

You are managing a project which is in the middle of the executing effort. You receive a call from a stakeholder and he is suggesting a change which would lead to the second major overhaul of the project. Also, the project manager just found out that a large work package was not completed. It happened because a team member's manager moved him to another project. Who should the project manager contact to deal with the issue?