You are managing a project which is in the middle of the executing effort. You receive a call from a stakeholder and he is suggesting a change which would lead to the second major overhaul of the project. Also, the project manager just found out that a large work package was not completed. It happened because a team member's manager moved him to another project. Who should the project manager contact to deal with the issue?