PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconResource Management

Nancy is the project manager of a project. Her team is experiencing some trouble with a new material that the project will utilize. Nancy gathers the team to lead an active problem-solving session. Which one of the following is the best definition of active problem solving?