PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconResource Management

The project manager is working on a project with a very tight schedule. The project is running late and the project manager believes that he does not have time to consider all the possible solutions that two team members are arguing over. He decides to go with the team member with the largest amount of seniority. This is an example of: