lock iconResource Management

While managing a project to develop a new software for a consulting company, you request four additional resources from different functional areas. The functional managers are reluctant to assign their resources to your project. However, they agree to allow you obtain the requested resources on condition that you give up some other resources at an earlier date that originally planned. What conflict resolution technique is being used?