PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconRisk Management

There is a risk event that has 90 percent chance of happening and it will cost the project $10,000. What does $9,000 represent?