PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconRisk Management

Jacob is a project manager for the construction of a major manufacturing plant. His team consists of members from 10 different countries that work in their own time zones. During the project planning, the team is struggling to come up with an effective way to mitigate or insure against a risk. This work cannot be outsourced or deleted. What is the best solution?