lock iconRisk Management

You have been managing a rail construction project. Most of the negavite events that have been predicted have happened. There are 6 activities left and three of them are on the critical path. Almost all the reserve has been used in the last half a year. Today, on the meeting the management informed you that they want to finish the project 10 days earlier. After the meeting, you sent out a request for proposal for some work that the team was going to do trying to find another company that could perform the work faster. In other words, you are trying to work with: