PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconRisk Management

George is a project manager and his team is very experienced. Right now, they are working on creating a project management plan. Today, the management requested them to identify project risks and provide some qualitative output as soon as possible. The team should provide: