Risk Management
You are the project manager for the project that will create a new web site for your organization. You would like to poll experts within your organization with a simple, anonymous form asking about any foreseeable risks in the design, structure and intent of the web site. With the collected information, these anonymous polls are submitted to the group of experts. This is an example of: