lock iconRisk Management

You are managing a project to renew the filtration system in a large swimming pool. You realize that the risks associated with handling certain equipment are too high. You have decided to allow someone else to complete this part of the project, so you outsourced the handling and installation of the filter equipment to an experienced contractor. This is an example of: