3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconRisk Management

While managing a critical project, the project manager reviewed and verified all documented assumptions from the team and verified the source of data used in the process of identifying and rating risks. The team identified 25 potential risks, determined what would trigger the risks, rated and ranked each risk using a risk rating matrix. What important action has been missed?