lock iconSchedule Management

The customer is asking to finish the project earlier, even though the original project schedule was agreed upon. The sponsor of the project manager thinks that it is possible to do so. He also believes it will serve the company good because they would be able to start a new project sooner. In order to complete the project earlier, the project manager looks at the cost associated with crashing each activity. The best approach to crashing would also include looking at: