lock iconSchedule Management

You are managing a project with the budget of $100.000 over a two-month period. As of today, the project should have cost $50.000, according to the schedule. But it cost $70.000 instead. Also, due to inaccurate original estimates, the project is behind schedule. The responsibility to deal with the problem would lie with: