PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconSchedule Management

You are managing a project with the budget of $100.000 over a two-month period. As of today, the project should have cost $50.000, according to the schedule. But it cost $70.000 instead. Also, due to inaccurate original estimates, the project is behind schedule. The responsibility to deal with the problem would lie with: