Schedule Management
You've been managing projects for an interior and exterior design company for 10 years. In your current project to decorate museum halls, the walls are scheduled to be painted immediately after the primer. You have allowed 24 hours between the primer activity and the painting activity to ensure that the primer has cured. This is an example of: