lock iconSchedule Management

You are managing a project to complete the drilling of a well in Louisiana. The specification of the well is documented, but your company has no experience working in Louisiana. The stakeholder is worried that your time estimates are not accurate due to many water-saturated coastal and swamp regions of the state. Which one of the following can you use to ensure your project estimates are accurate?