PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconSchedule Management

You are managing a project to complete the drilling of a well in Louisiana. The specification of the well is documented, but your company has no experience working in Louisiana. The stakeholder is worried that your time estimates are not accurate due to many water-saturated coastal and swamp regions of the state. Which one of the following can you use to ensure your project estimates are accurate?