lock iconSchedule Management

There are 10 highly experienced employees on your project team. You disagree with one of them on the time allotted to complete some activities. This team member wants to bloat the time associated with activities to ensure he will have enough time to complete his tasks should some risk events cause the schedule to change. Instead of overestimating his project activities, the project team member should use: