lock iconSchedule Management

You are managing a project to create a drone capable of lifting up to 10 pounds. While reviewing the project, you notice that activities were scheduled in sequential order, but technical work was initiated 14 days earlier than planned. What type of relationship represents the start of the technical work to the completion of the design work?