lock iconSchedule Management

You've been requested by the sponsor to shorten the project's duration. With the management's approval, you decide to perform a few activities in parallel rather than in sequential order as originally planned. You decide to do it despite the fact that this option will probably lead to rework, increase risks and require more communication. This is an example of: