PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconSchedule Management

A bridge reconstruction project has been assigned to the project manager. His team worked with the WBS for a while and completed the decomposition of the work packages. In 10 days the estimates of all activities were finalized and the network diagram was completed by the team. Which activities will be next to focus on for the project manager?