4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

You and your team are very positive about the current project. The value of the work completed today is $50 million. Focus groups gave wonderful reviews and can't wait for the product to become available on the market. The phase gate review board has received the reports and is asking for market projections and launch plans. They want to know when the product can start returning value to the company. The project is budgeted to cost $85 million. The value of the work planned to be done to this point is $87 million. According to the schedule performance index (SPI) you are: