Scope Management
The project manager has been assigned to a project to create and implement a new office software that would run identification checks on authorized users and automatically insert electronic signatures where required. This would ease the workload for many employees of the company and take their performance to another level. The management informed you that the application must work on the existing infrastructure and if needed, should be easily integrated with all other applications the organization is currently using. This is an example of: