You were managing a project to construct a major pedestrian bridge. In the initial design, the bridge was straight and had enough width for emergency vehicles. The management asked you to study the work method to determine a less costly and more effective way to complete the project. You met with the local emergency services and discovered that emergency vehicle access was not necessary. Also, after consulting with the public, it was determined that a curved, aesthetic bridge was in the best interests of the public in this location instead of a straight bridge (it was alongside a freeway crossing). The design changes were significant, but the end result was less costly while providing a better product. This was an example of: