PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

Imagine the following situation. You are a project manager of the project which is in its completion stage. You have a request from the sponsor to prepare the report of how the project is going. You ask all the team members what percent complete their work is in order to prepare such a report. There is one team member who was hard to cooperate with from the beginning and when you ask him 'What percent complete are you?', he answers 'Percent of what?'. You've had enough of similar comments and now you report to the team member's boss that the team member is not cooperating. Most likely the real problem is the following: