PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

You are managing the project on construction of the highest building in town. During the planning phase, your project team has discovered another method to complete a portion of the project scope. This method may be more expensive for the customer, but it's safer for the project team. This is an example of: