PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

You have been assigned to a major project from a large cruise company. Many requirements have to be documented, annotated and communicated to the project stakeholders. Management would also like you to report when the requirements should be created and when they’re created by the project team. What document will help you monitor all the characteristics of each requirement?