lock iconScope Management

You are one of the most experienced project managers in the company. You have been assigned to a project to create a new product for car industry. You have recently learned your competitor is also working on a similar project, but their offering will include web-based tools, which your project does not offer. You have implemented a change request to update your project. This is an example of: