PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

You are one of the most experienced project managers in the company. You have been assigned to a project to create a new product for car industry. You have recently learned your competitor is also working on a similar project, but their offering will include web-based tools, which your project does not offer. You have implemented a change request to update your project. This is an example of: