PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

One of the project managers in your organization left the company for personal reasons. The project he was managing was to introduce a new system of id verification over the phone for a bank. You were assigned to take over this project when it was ready to enter execution. When you looked through existing documents you realized that the project team did a great job developing the requirements documents and the project scope statement, but there was no WBS. What should you do in the first place in this situation?