Stakeholder Management
The requirements of several stakeholders were not included in the project due to budget constraints. The project manager finalized the project management plan, but encountered challenges in receiving formal acceptance. The stakeholders were very upset and tried every possible way to include their requirements in the project. The project got finally approved after a few attempts and it was initiated three months ago. Which of the following preventive actions the project manager should not consider in this case?