PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconStakeholder Management

Identification of internal and external stakeholders in the construction project has been recently completed by the project manager. There are 20 stakeholders on the list. The project manager expects that most of stakeholders will contribute to the project. While working on the project management plan, the project manager learned from one of the team members that one stakeholder is missing in the list of stakeholders. What should the project manager do in the first place?