Too many changes to the project you are managing have been made. You are an experienced project manager with technical expertise and good communications and management skills. The team has chosen the appropriate processes for use on the project. The product will be installed in all the departments of the company and it will considerably improve departmental performance when operational. What could most likely cause the project changes?