You have been assigned to a project to create a website. One of the stakeholders involved has a reputation for requesting many changes on projects. The website you need to create will have a couple of features the stakeholder's clients will use. However, the clients in this business unit will use the website only occasionally. The best approach for the project manager to take at the beginning of the project to manage this situation is: