You have been assigned to a project to develop an application for an airline company to allow passengers exchange seats while on board the plane. This kind of a project is totally new for you and your team. The application is interactive and complex. The timeline for the project is aggressive. You and the sponsor achieved agreement and sign-off on both the project charter and the project management plan. Client personnel is keeping track of the progress of the project through status reports and regular meetings. The project is within budget and on schedule. Also, a final perfunctory review has been scheduled. Today you have been informed that the entire effort might be cancelled because the product being developed is unacceptable. The most likely cause of this situation is that: