You are managing the development of a website. Some of your close friends will be using the website when the project is complete and the website is rolled out. At a Christmas party, you accidentally learn from those friends that they consider some aspects of the current website extremely annoying. You pass this information along to the sponsor and encourage scope and design changes. How can you best describe you action?