The project manager has been assigned to a large-scale construction project. The project will construct a new tunnel in the city. The project manager is preparing for stakeholder identification because he wants to capture all the internal and external stakeholders who may influence and be influenced by this project. In his preparations, the project manager will need all the following documents as inputs EXCEPT: