lock iconStakeholder Management

Robert is the project manager of a new software deployment project. This project will affect 1100 people in his organization. He’s communicated the deployment and explained the effect the software will have on the organization and his plan includes training for the end users. Some of the stakeholders, especially the functional managers, are worried about the deployment and how it will affect the company's productivity. Linda, the project sponsor, asks Robert to create a visual diagram showing which stakeholders can affect the project the most based on their power in the organization. What type of chart should Robert create?