PMP Exam Simulator
3h 50m 0s
Stakeholder Management
Julia is the project manager for a bridge construction project. This project has internal and external stakeholders, including members of the community who are opposed to the project, although it has been approved by the city. Julia wants to create a stakeholder engagement plan and she’s gathering several inputs for the plan’s creation. Which one of the following inputs will most help Julia create a strategy for stakeholder management and engagement?