PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconStakeholder Management

You are the project manager of a large construction project. Your project has been in motion for two months and you’re about to move into the first phase of project execution. Your sponsor informs you that you’ve apparently overlooked some stakeholders during the project’s planning phase. What should you do?