The project you are managing is scheduled to last 20 months and will affect 350 stakeholders in your company. The project has sensitive information that only certain stakeholders should have access to. You’ve created a plan for communicating the information to the correct parties throughout the project through special e-mail bulletins. What type of communication is secured e-mail considered to be?