PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconStakeholder Management

The project you are managing is scheduled to last 20 months and will affect 350 stakeholders in your company. The project has sensitive information that only certain stakeholders should have access to. You’ve created a plan for communicating the information to the correct parties throughout the project through special e-mail bulletins. What type of communication is secured e-mail considered to be?