PMP Exam Simulator
3h 50m 0s
Stakeholder Management
You are a project manager and right now you are trying to identify stakeholders who may be affected by your project. For that purpose, you are looking through the organizational structure of your client's organization. After you identify stakeholders on the organizational chart, you arrange meetings with each stakeholder. All the information you learn about stakeholders will be documented in the stakeholder register. This register can then be used as an input to which of the following processes?