A project just started the phase in which work packages are being created. Bryan started working in the company recently and he asked you, the project manager, to validate the scope of his work packages that he had just completed. Bryan is very nervous to have the customer see his work packages. You think that Brian did a great job and at the same time you want Bryan to get more confidence after the customer sees his work packages. The Validate Scope process should be done: