lock iconScope Management

Laura has been working on projects for the last 6 years. Now she joined the project management office. She wants to introduce the value of creating and utilizing work breakdown structures. Some of the project managers are not happy at all to be asked to do 'extra work'. What can Laura tell the project managers in order to convince them to use work breakdown structures?