PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCommunications Management

Jeffrey is a new project manager of the construction of a huge playground. There are a few team members those native language is not English. Jeffrey is constantly using technical jargon from his former company when discussing work activities with the team. This jargon is unfamiliar to these team members whose native language is not English. What is the major result of communication blockers?