lock iconCommunications Management

Julia is a project manager of a large organization. She is managing an international project with stakeholders in four countries: Germany, France, Italy and the USA. In this project, Julia will need to plan for project assumptions and constraints that affect how she and the other project stakeholders will communicate. Which one of the following is an example of a project communication constraint?