Cost Management
The project manager is working on the project to clear dangerous lead paint from 15 miles of the city's subway stations and repaint them. He was supposed to spend $10,000 per mile and the project was supposed to be completed today, which is exactly 30 weeks after the project started. The project manager realizes that only 75% of the work has been completed so far. What is the Budget at Completion (BAC)?