PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

A project manager had prepared a project cost estimate and delivered it to the project sponsor at the meeting. Unfortunately, the sponsor was unsatisfied with the estimate. He expects the project manager to cut 20 percent from the project estimate. The best thing for the project manager to do is: