lock iconCost Management

A project manager had prepared a project cost estimate and delivered it to the project sponsor at the meeting. Unfortunately, the sponsor was unsatisfied with the estimate. He expects the project manager to cut 20 percent from the project estimate. The best thing for the project manager to do is: