PMP Exam Simulator

alarm icon
4h 0m 0s
info iconPMP exam lasts 4h and has 200 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

While managing a project to install a new software on twenty computers, the project manager reviews an earned value report. The SPI is 1.1 and the CPI is 0.8. Which statement is TRUE about the project?