PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

You are managing a project to update the application for a medical office. While reviewing the project status, you find out that EV = 324,000, AC = 240,000 and PV = 343,000. Now you need to calculate SPI and CPI. What are the SPI and the CPI in this project?