PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconCost Management

There are 14 components to work on for the project manager in his current project. According to his estimation, the first 6 components will cost $1,400 each and the remaining 8 components will cost $1,300 each. The schedule projected that today the project manager would be done with 40% of the components. While collecting the status updates from the team, the project manager found out that the first 5 components were completed at a cost of $7,500. What is the SPI?